New Road For Hang Dong

 | Fri 27 May 2016 09:33 ICT

CityNews – The building of a road from Tha Wang Phrao intersection to Ton Kwen intersection in San Pa Tong, Hang Dong, has been given the go ahead, with work expected to finish within the next two years.

new road

The Director of the Department of Rural Roads Chiang Mai, Apichai Teeraungsikul, said that the new road will stretch for 27.8 km and have a central barrier with five u-turn junctions.

The construction company is the Siamphan Enterprise Public Company Limited, with a plan that will complete in 780 days, in June 2018.

The road will cost 402 million nine hundred and fifty thousand baht.